Laws of Malaysia·Act 746
CONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT 2012
AKTA PEMBAYARAN DAN ADJUDIKASI INDUSTRI PEMBINAAN 2012
Official editions
- English editionCONSTRUCTION INDUSTRY PAYMENT AND ADJUDICATION ACT 2012
- Edisi Bahasa MelayuAKTA PEMBAYARAN DAN ADJUDIKASI INDUSTRI PEMBINAAN 2012
Business activities this Act regulates
We haven't mapped this Act to specific MSIC business activities. Many federal Acts are general statutes (company law, employment, taxation, procedure) that apply across business activities generally rather than regulating one industry. Where an Act governs a specific licence, the regulated activities appear here.
Consolidated text (extract)
Construction Industry Payment and Adjudication
laws OF MALAYSIA
Act 746
construction industry payment and
adjudication act 2012
1
2
Laws of Malaysia
Date of Royal Assent
Act 746
...
...
18 June 2012
Date of publication in the
Gazette
...
...
...
22 June 2012
Publisher’s Copyright C
percetakan nasional malaysia berhad
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means
electronic, mechanical, photocopying, recording and/or otherwise without the prior permission of Percetakan Nasional Malaysia Berhad
(Appointed Printer to the Government of Malaysia).
Construction Industry Payment and Adjudication
laws of malaysia
Act 746
construction industry payment and
adjudication act 2012
ARRANGEMENT OF sections
Part I
PRELIMINARY
Section
1. Short title and commencement
2.
3.
Application
Non-application
4. Interpretation
Part II
ADJUDICATION OF PAYMENT DISPUTES
5.
Payment claim
7.
Right to refer dispute to adjudication
6.
Payment response
8. Initiation of adjudication
9.
Adjudication claim
11.
Adjudication reply
10.
12.
13.
Adjudication response
Adjudication and decision
Effect of adjudication decision
14. Consolidation of adjudication proceedings
15. Improperly procured adjudication decision
16. Stay of adjudication decision
17.
Withdrawal and recommencement of adjudication proceedings
19.
Adjudicator’s fees and expenses, etc.
18. Costs of adjudication proceedings
20. Confidentiality of adjudication
3
4
Laws of Malaysia
Act 746
Part III
ADJUDICATOR
Section
21.
Appointment of adjudicator
22.
Appointment of adjudicator by parties
23.
Appointment of adjudicator by Director of the KLRCA
24.
Duties and obligations of the adjudicator
25.
Powers of the adjudicator
26.
Power of adjudicator not affected by non-compliance
27.
Jurisdiction of adjudicator
Part IV
ENFORCEMENT OF ADJUDICATION DECISION
28.
Enforcement of adjudication decision as judgment
29. Suspension or reduction of rate of progress of performance
30.
Direct payment from principal
31. Concurrent exercise of remedies
Part V
ADJUDICATION AUTHORITY
32.
Functions of KLRCA
33.
Policy directions
Part VI
GENERAL
34. Immunity of adjudicator and KLRCA
35.
Prohibition of conditional payment
36.
Default provisions in the absence of terms of payment
37.
Relationship between adjudication and other dispute resolution process
Construction Industry Payment and Adjudication
Part VII
MISCELLANEOUS
Section
38. Service of notices and documents
39.
40.
Regulations
Exemption
41. Savings
5
6
Laws of Malaysia
Act 746
7
Construction Industry Payment and Adjudication
laws of malaysia
Act 746
construction industry payment
and adjudication act 2012
An Act to facilitate regular and timely payment, to provide a
mechanism for speedy dispute resolution through adjudication, to
provide remedies for the recovery of payment in the construction
industry and to provide for connected and incidental matters.
[
]
ENACTED by the Parliament of Malaysia as follows:
Part I
PRELIMINARY
Short title and commencement
1. (1) This Act may be cited as the Construction Industry Payment
and Adjudication Act 2012.
(2) This Act comes into operation on a date to be appointed
by the Minister by notification in the Gazette.
Application
2. This Act applies to every construction contract made in writing
relating to construction work carried out wholly or partly within
the territory of Malaysia including a construction contract entered
into by the Government.
8
Laws of Malaysia
Act 746
Non-application
3. This Act does not apply to a construction contract entered
into by a natural person for any construction work in respect of
any building which is less than four storeys high and which is
wholly intended for his occupation.
Interpretation
4. In this Act, unless the context otherwise requires—
“adjudication decision” means the decision made by an adjudicator
under subsection 12(2);
“adjudication proceedings” means the process of adjudication
under this Act;
“adjudicator” means an individual appointed to adjudicate a
dispute under this Act;
“claimant” means an aggrieved party in a construction contract
who initiates adjudication proceedings;
“construction consultancy contract” means a contract to carry out
consultancy services in relation to construction work and includes
planning and feasibility study, architectural work, engineering,
surveying, exterior and interior decoration, landscaping and project
management services;
“construction contract” means a construction work contract or
construction consultancy contract;
“construction work” means the construction, extension,
installation, repair, maintenance, renewal, removal, renovation,
alteration, dismantling, or demolition of—
(a) any building, erection, edifice, structure, wall, fence or
chimney, whether constructed wholly or partly above or
below ground level;
(b) any road, harbour works, railway, cableway, canal or
aerodrome;
(c) any drainage, irrigation or river control work;
Construction Industry Payment and Adjudication
9
(d) any electrical, mechanical, water, gas, oil, petrochemical
or telecommunication work; or
(e) any bridge, viaduct, dam, reservoir, earthworks, pipeline,
sewer, aqueduct, culvert, drive, shaft, tunnel or reclamation
work,
and includes—
(A) any work which forms an integral part of, or are preparatory
to or temporary for the works described in paragraphs
(a) to (e), including site clearance, soil investigation
and improvement, earth-moving, excavation, laying of
foundation, site restoration and landscaping; and
(B) procurement of construction materials, equipment or
workers, as necessarily required for any works described
in paragraphs (a) to (e);
“construction work contract” means a contract to carry out
construction work;
“contract administrator” means an architect, engineer,
superintending officer or other person howsoever designated who
administers a construction contract;
“Government” means the Federal Government or the State
Government;
“High Court” means the High Court in Malaya or the High
Court in Sabah and Sarawak, as the case may require;
“KLRCA” means the Kuala Lumpur Regional Centre for
Arbitration;
“Minister” means the Minister charged with the responsibility
for works;
“non-paying party” means a party against whom a payment
claim is made pursuant to a construction contract;
“payment” means a payment for work done or services rendered
under the express terms of a construction contract;
10
Laws of Malaysia
Act 746
“principal” means a party who has contracted with and is liable
to make payment to another party where that other party has in
turn contracted with and is liable to make payment to a further
person in a chain of construction contracts;
“respondent” means the person on whom the notice of adjudication
and adjudication claim has been served;
“site” means the place where the construction work is affixed
whether on-shore or off-shore;
“unpaid party” means a party who claims payment of a sum
which has not been paid in whole or in part under a construction
contract;
“working day” means a calendar day but exclude weekends
and public holidays applicable at the State or Federal Territory
where the site is located.
Part II
ADJUDICATION OF PAYMENT DISPUTES
Payment claim
5. (1) An unpaid party may serve a payment claim on a nonpaying party for payment pursuant to a construction contract.
(2) The payment claim shall be in writing and shall
include—
(a) the amount claimed and due date for payment of the
amount claimed;
(b) details to identify the cause of action including the
provision in the construction contract to which the
payment relates;
(c) description of the work or services to which the payment
relates; and
(d) a statement that it is made under this Act.
Construction Industry Payment and Adjudication
11
Payment response
6. (1) A non-paying party who admits to the payment claim
served on him shall serve a payment response on the unpaid
party together with the whole amount claimed or any amount as
admitted by him.
(2) A non-paying party who disputes the amount claimed in
the payment claim, either wholly or partly, shall serve a payment
response in writing on the unpaid party stating the amount disputed
and the reason for the dispute.
(3) A payment response issued under subsection (1) or (2)
shall be served on the unpaid party within ten working days of
the receipt of the payment claim.
(4) A non-paying party who fails to respond to a payment
claim in the manner provided under this section is deemed to
have disputed the entire payment claim.
Right to refer dispute to adjudication
7. (1) An unpaid party or a non-paying party may refer a
dispute arising from a payment claim made under section 5 to
adjudication.
(2) The right to refer a dispute to adjudication shall only
be exercised after the expiry of the period to serve a payment
response as specified under subsection 6(3).
(3) A dispute referred to adjudication under this Act is subject
to the Limitation Act 1953 [Act 254], Sabah Limitation Ordinance
[Cap. 72] or Sarawak Limitation Ordinance [Cap. 49] as the case
may be.
Initiation of adjudication
8. (1) A claimant may initiate adjudication proceedings by
serving a written notice of adjudication containing the nature and
description of the dispute and the remedy sought together with
any supporting document on the respondent.
12
Laws of Malaysia
Act 746
(2) Upon receipt by the respondent of the notice of adjudication,
an adjudicator shall be appointed in the manner described in
section 21.
(3) A party to the adjudication proceedings may represent
himself or be represented by any representative appointed by the
party.
Adjudication claim
9. (1) The claimant shall, within ten working days from the
receipt of the acceptance of appointment by the adjudicator
under subsection 22(2) or 23(2), serve a written adjudication
claim containing the nature and description of the dispute and
the remedy sought together with any supporting document on the
respondent.
(2) The claimant shall provide the adjudicator with a copy of
the adjudication claim together with any supporting document
within the time specified under subsection (1).
Adjudication response
10. (1) The respondent shall, within ten working days from the
receipt of the adjudication claim under subsection 9(1), serve a
written adjudication response which shall answer the adjudication
claim together with any supporting document on the claimant.
(2) The respondent shall provide the adjudicator with a copy of
the adjudication response together with any supporting document
within the time specified under subsection (1).
(3) If the respondent fails to serve any adjudication response,
the claimant may proceed with the adjudication after the expiry
of the time specified under subsection (1).
Adjudication reply
11. (1) The claimant may, within five working days from the
receipt of the adjudication response, serve a written reply to the
adjudication response together with any supporting document on
the respondent.
Construction Industry Payment and Adjudication
13
(2) The claimant shall provide the adjudicator with a copy of
the adjudication reply together with any supporting document
within the time specified under subsection (1).
Adjudication and decision
12. (1) The adjudicator shall conduct the adjudication in the
manner as the adjudicator considers appropriate within the powers
provided under section 25.
(2) Subject to subsection 19(5), the adjudicator shall decide
the dispute and deliver the adjudication decision within—
(a) forty-five working days from the service of the adjudication
response or reply to the adjudication response, whichever
is later;
(b) forty-five working days from the expiry of the period
prescribed for the service of the adjudication response
if no adjudication response is received; or
(c) such further time as agreed to by the pa
Extract truncated for display. Download the official PDF above for the full text.